Posted on: November 4, 2016

[ARCHIVED] Williams Trace Reconstruction Phase I

Update: December 4: 2017

Williams Trace Blvd. - Traffic Switch Postponed
Weather permitting a traffic switch will be implemented on Williams Trace Blvd. from south of State Highway 6 through the intersection of Austin Parkway on Monday December 11. The roadway will be opened to traffic on both sides of the boulevard up to the commercial area at State Highway 6 where the remaining approximately 400 feet of roadway connecting to State Highway 6 has to be completed in three segments. This final phase of the project is expected to last 8 weeks.


Residents are asked to be mindful of work crews, expect traffic delays, and when possible, avoid the area to prevent traffic congestion. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.

------------------------------------------

 Update: December 4, 2017

Williams Trace Blvd. - Traffic Switch

Weather permitting, a traffic switch will be implemented on Williams Trace Blvd. from south of SH 6 through the intersection of Austin Parkway on Friday, December 8. The roadway will be opened to traffic on both sides of the boulevard up to the commercial area at SH 6. This final phase of the project is expected to last 8 weeks.


 

Update: November 29, 2017

Williams Trace Blvd. - Traffic Switch

A traffic switch will be occur on Williams Trace Blvd. from south of SH 6 through the intersection of Austin Parkway on Monday December 4. The roadway will be opened to traffic on both sides of the boulevard up to the commercial area at SH 6. This final phase of the project is expected to last 8 weeks.

------------------------------------------

Update: September 26, 2017

Countryside Drive - Traffic Detour

Countryside Drive will be closed at the intersection of Williams Trace Boulevard until October 18 . Traffic will be detoured to Planters Drive and Greenfields Drive. The detour is taking place to allow for storm sewer, utility, and paving installation.

------------------------------------------

Initial Message

Phase I of the Williams Trace Reconstruction project is scheduled to begin on January 2017. The overall scope of the project is as follows:

  • Full replacement of the roadway, from SH 6 through Austin Parkway
  • Full replacement of the existing water main (due to age and material type)
  • Upgrade of the existing traffic signals at Austin Parkway
  • Construction of an additional parallel storm sewer along the project corridor to correct drainage deficiencies
  • Construction of a 10-ft sidepath along Williams Trace from Austin Parkway to SH6

Updates will be posted on this website in addition to advance notices given for temporary water service outages and road closures.


Project documentation is available below:

Project: Williams Trace Reconstruction Phase I, CIP # ST1408

Project Manager: Ross Woodfin

Engineering Department: (281) 275-2780