Posted on: April 27, 2017

Lexington Blvd. & Highlands Section III Drainage Improvements

Update: June 14, 2017

Lexington Blvd. and Settlers Way Blvd. - Alternating Lane Closures

Alternating lane closures will be taking place at the intersection of Lexington Blvd. and Settlers Way Blvd. from June 14 through June 30. The lane closures are taking ...

Read on...

Posted on: March 10, 2017

SH 6 and US 90A - Temporary Lane Closures

Over the next three months, temporary lane closures may occur during the off-peak hours from Monday through Saturday (9 a.m. - 4 p.m.) at the following locations:

  • SH 6 southbound (south of Voss Rd.)
  • US 90A eastbound and westbound (at Parklane Blvd.)
  • US 90A e...
Read on...

Posted on: January 23, 2017

Kempner Street Construction, Wood Street Closure

Update: Feb. 2 The University Blvd. crossing is scheduled to open on Monday, February 6, after the morning peak hour. If horns are blowing or gate arms are down for an extended period time, motorists are asked not to place themselves in danger by gettin...Read on...
Posted on: January 5, 2017

Covington Woods, Ivymount – Drainage Improvement Project

Construction activities are scheduled to begin in February of 2017. Pre-construction activities may have already begun in some neighborhoods.

In addition:

  • Construction work is scheduled for 180 calendar days
  • The work will be done in phases and sequenc...
Read on...

Posted on: December 9, 2016

Convington Woods – Drainage Improvements

The Covington Woods Bournewood Trunkline project is scheduled to begin on January 2017. Temporary water service outages and road closures can be expected in the Covington Woods neighborhood. Streets affected include:

  • Bournewood Dr.
  • Ravenscourt Dr.
  • Barrowgat...
Read on...

Posted on: December 9, 2016

Woodchester Water Plant - Ground Water Storage Tanks Rehabilitation

Construction work to rehabilitate the ground water storage tanks at the Woodchester Water Plant will begin this month. This work is expected to be finished by the end of 2017. Work is expected to occur from 7 a.m. to 6 p.m. Monday through Friday and may p...Read on...

Posted on: November 4, 2016

Williams Trace Reconstruction Phase I

Update: June 19, 2017

Austin Parkway - Traffic Switch

Austin Parkway will be switched to two-way traffic on the south side of the boulevard through the intersection of Williams Trace/ Sweetwater from June 21 until July 15. Paving and utility installation wi...

Read on...

Posted on: October 27, 2016

Williams Trace, Phase II - Alternating Lane Closures

Streetlight replacement will be taking place on Williams Trace between The Highlands and SH6. The project begins on October 31, weather permitting. Residents are asked to be mindful of work crews, expect traffic delays, and when possible, avoid the area ...Read on...
Posted on: September 8, 2016

Sugar Creek Drainage Improvements - Golf Course and Longview Dr.

Update: May 9, 2017 - Road Closure

Drainage, water and road improvements will require closure of the northbound east side of Longview Dr. (at about 623 Longview Dr.) until August 2017. Access will be restricted to residents of the area only.

Residents are a...

Read on...