[ARCHIVED] Greenfields Dr. and Mesquite Dr. - Full Closure

Update: June 19
A full closure of the intersection of Greenfields Dr. and Mesquite Dr. will begin on Wednesday, June 24. The closure is expected to last six weeks and the intersection will reopen before school starts. Installation of storm sewer lines and roadway replacement work will take place.

Traffic on Greenfields crossing the bridge (at the F.B.C.L.I.D. 2 Ditch) will be detoured to Austin Parkway Blvd.

Motorists should expect delays, adhere to all construction signage and be cautious in the immediate area. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.

---------------------------------------


Update: March 31, 2020
A one lane closure will take place on northbound Mesquite Dr. (from the corner near First Colony Middle School to the intersection of Green Fields Dr.) beginning on Monday, April 6. Northbound Mesquite Dr. traffic will be detoured to Green Fields Dr. This closure is taking place to allow for the installation of storm sewer and roadway replacement as part of the improvements project.

 Motorists should expect delays, adhere to all construction signage and be cautious in the immediate area. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.

---------------------------------------


Portions of the Settlers Park subdivision regularly experience excessive street ponding during major storm events. This project will provide improvements to the stormwater infrastructure and reduce street ponding during major storm events.

  • The project requires the replacement of the existing stormwater pipes along Greenfield Drive, Mesquite Drive, and Sleepy Hollow Drive with new larger stormwater pipe and the replacement of the outfall into FBC LID No. 2, Ditch C.
  • In addition, all street paving on those streets, sidewalks, driveways to the right of way lines, and portions water mains within the project limits will be replaced.

Traffic detours and some water service disruptions can be expected. The construction is scheduled to begin in March and is anticipated to be completed in thirteen (13) months.


CIP-DR1903_ProjectMap

If you should have any questions please contact Ross Woodfin, Sr. Project Manager, with the Engineering department at 281-275-2780.