Update: Tuesday, November 26
Work continues on drainage improvements, street reconstruction and water line rehabilitation along Muirwood Lane and 7th Street between the City-owned Park and Woodlake Circle.
The city is performing some additional survey and confirming design elevations for the Right-of-Way and driveways. A survey crew working for the city and one of our inspectors will be working during the next couple of days performing the survey of the street, sidewalk, and driveways next to the garage doors. Our contractor and inspector will be properly identified.
In addition, we request residents are asked to be mindful of work crews, expect traffic delays, and when possible, avoid the area to prevent traffic congestion. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.
Check out the CIP Story map for more information about this project.
------------------------------------------------------
Update: Monday, November 11
Muirwood Lane – Partial Closing
Partial closure of the northbound lane of Muirwood (around the area of 7th Street) will take place on November 18 through February 20, 2020.
During this time, all homes will have access to their driveways until work begins in front of their driveway, (approx. 5 driveways at a time). For 2 weeks, the residents of these 5 homes will be unable to access their driveways/garages, but they will be allowed to park down the street in the section that is not under construction. By the end of the 2nd week the portion of the street will be completed and driveway access will be restored. We appreciate residents' patience and cooperation.
--------------------------------
Update: Friday, November 8
The planned closure of the 7th Street and South Bournewood Dr. intersection scheduled for Monday, November 11 has been postponed. A notification will be sent out once the closure is rescheduled.
---------------------------------
Update: November 5, 2019
7th Street and Bournewood Dr.– Partial Intersection Closing
A partial closure of the instersection of 7th Street and Bournewood Dr. will take place strating on Monday, November 11 through November 22 as work continues on drainage improvements, street reconstruction and water line rehabilitation.
Please note:
- The southbound lane of Bournewood will be closed to traffic.
- Only northbound traffic will be allowed at Bournewood Dr. and 7th Street.
- Bournewood Dr. southbound traffic will be detoured via Greenbelt Dr. to West Greenbelt to 7th Street
-----------------------------------
Update: October 4, 2019
The current closure of the intersection of 7th Street and West Green Belt will continue through Monday, October 28, 2019. Westbound traffic on 7th St. will be detour north on Bournewood Dr. to Jess Pirtle Blvd.
-----------------------------------
The intersection at West Green Belt and 7th Street will be closed to traffic from September 19 to October 10, 2019. In addition, the westbound lane of 7th Street will be closed to traffic from West Green Belt to Bournewood Drive starting October 2019 through December 2019. Traffic will flow only in one direction (West to East).
Project: Covington Woods Drainage Improvements - Sugar Land MS/Sugar Mill Relief Line (DR1801)
Project Manager: Jorge Alba (281) 275-2275
Engineering Department: (281) 275-2780