[ARCHIVED] Citywide Sewer Collection System Rehabilitation

Update: July 31 | Lakeside Plaza Dr. and Target Area - Take Caution
Sanitary sewer work along the southbound US 59 feeder road (between Hwy 6 and the north treatment plant) is progressing. This construction work will require a ramp structure to be used on Lakeside Plaza Drive and the driveway into the Target area parking lot. A second crew is completing sanitary sewer work on Foxbriar Drive in the Sugar Creek area.

Motorists are asked to use caution, cross the ramps slowly and be mindful of work crews during this time. Visit its.sugarlandtx.gov for more information on Sugar Land travel data.
-----------------------------------------

Update: April 22 | Lake Pointe Pkwy and Whole Foods Area Driveway – Take Caution
Sanitary sewer work along the southbound US59 feeder road (between Lake Point Pkwy. and Hwy 6) is scheduled for April 22. This construction work will require a ramp structure to be used on Lake Pointe Pkwy and the driveway into the Whole Foods area parking lot.

-----------------------------------------

Update: February 7
Work activity is progressing from Sugar Creek Center Blvd. towards the southbound portion of the US59 feeder road. Additional work activity will be moving from the Mayfield park area to The Hill on Monday, February 11.

-----------------------------

Update: January 31, 2019

Sugar Creek Center Blvd. will be reduced to one lane in each direction starting Monday, February 4, 2019. The closures are expected to last approximately one week.

--------------------------

Update: January 22, 2019
Work crews will be moving into the Mayfield Park area today, January 22, 2019.

------------------------------

Update: January 17, 2019

The scheduled work and lane reductions on Sugar Creek Center Blvd. scheduled for Monday, January 21 will be postponed until further notice.

------------------------------

Update: January 15, 2019

Current lane closures on Sugar Creek Center Blvd. will reopen Wednesday through Sunday. One-lane closures in each direction will once again take place starting Monday, January 21 through Wednesday, January 23.

Residents are asked to be mindful of work crews during this time.  Visit its.sugarlandtx.gov for more information on Sugar Land travel data.

------------------------------

Update: January 10, 2019

Sugar Creek Center Blvd. will be reduced to one lane in each direction starting Monday, January 14, 2019. An additional crew will be working in the Sugar Creek Center area. The closures are expected to last approximately one week.

------------------------------

Update: January 7, 2019

The scheduled work and lane reductions scheduled for Monday, January 7 will be rescheduled.

------------------------------

Update: January 3, 2019

Sugar Creek Center Blvd. will be reduced to one lane in each direction starting Monday, January 7, 2019. An additional crew will be working in the Sugar Creek Center area. The closures are expected to last approximately one week.

------------------------------

Posted: October 23, 2018

The sanitary sewer collection system rehabilitation project is scheduled to begin November 5, 2018 in the Covington Woods area. Residents can expect construction equipment and activity in the neighborhood. Individual advance notices will be provided to those addresses that will be directly impacted. More information about this project is available on the CIP Story Map.

Project: Collection System Rehabilitation Project D Package # 2 (CIP WW1601)
Project Manager: Greg Nichols
Engineering Department: (281) 275-2780