PROPOSITION B PROJECT
Traffic Signal Rehabilitation
$4.65M

The City's traffic signal hardware and structures are aging with some traffic poles showing signs of fatigue. This suggests that the infrastructure may be reaching the end of its useful life.

The City maintains 92 signalized intersections including the traffic signals along major state roadways like SH6, US59, and US90.

Traffic Signal Maintenance

2024 Bond Project

Evaluation, design, and replacement of aging traffic signal infrastructure.

Funding: 2024 GO Bond - $4,650,000
Project Manager: James Turner
CIP #: CTR2502

CONSTRUCTION STARTED
JAN 2025

CURRENT PROJECT PHASE
PER/STUDY

Learn more about project phases

ESTIMATED COMPLETION
SEP 2029