PROPOSITION B PROJECT
Dulles Avenue Sidewalk Widening & Pedestrian Bridges*
$3.475M

The City's Mobility Master Plan outlines the vision of superior mobility in Sugar Land. Dulles Ave was identified as a high priority corridor for improvements in the plan. This project expands on recent construction done near the intersection at Avenue E by extending connectivity and safety for pedestrians and bicyclists along Dulles Ave. south to Oyster Creek.

Dulles Avenue

Dulles Avenue

2024 Bond Project

Install 10-ft wide side path on one side of street; install pedestrian bridge over American Canal near Riverbend Country Club; install pedestrian bridge over Ditch B; Dulles Ave midblock crossing connection to Missouri City Oyster Creek Trail w/pedestrian bridge over Oyster Creek.

Funding: 2023 FBC Mobility Bond - $2,750,000; 2024 GO Bond - $3,475,000
Project Manager: Huy Ton
CIP #: CTR2802

ESTIMATED CONSTRUCTION START
OCT 2029

CURRENT PROJECT PHASE
PER/STUDY

Learn more about project phases

ESTIMATED COMPLETION
APR 2031