PROPOSITION C PROJECT
Chatham at McAllister Drainage Modifications
$5.35M

The City has received resident concerns regarding the performance of the storm sewer in this area. The City completed a drainage study in 2023 that recommended modifications to the storm sewer system to address resident concerns.

Chatham at McAllister

Chatham at McAllister Intersection

2024 Bond Project

Enlarge storm sewer main line along Chatham Ave from the Telfair Community Park to McAllister and along Greyben, Furman, Somerset, Olmstead, Pickney, Whitman, Ogden.

Funding: 2024 GO Bond - $5,350,000
Project Manager: Huy Ton
CIP #: CDR2602

ESTIMATED CONSTRUCTION START
OCT 2027

CURRENT PROJECT PHASE
DESIGN

Learn more about project phases

ESTIMATED COMPLETION
APR 2029