The City of Sugar Land's Capital Improvement Program (CIP) furthers our commitment to meet today's needs as well as those of the future. From work on underground water and sewer lines to more visible projects such as street paving and the construction of a new City Hall at Town Square, the five-year CIP addresses the needs of the City through responsible City government with a comprehensive and cost-effective approach. For a detailed explanation of the City's CIP program please click here.
Any questions concerning CIP's may be directed to public works at publicworks@sugarlandtx.gov or telephone us at 281-275-2450.
Wastewater Projects
Wastewater projects include lift station rehabilitation at Ragus Lakes and Mayfield Park, rehabilitation of the collection system, land/ROW acquisition for diversion of flow from the north treatment plant to the west treatment plant, and emergency power for treatment plants.
FY09 design projects include the west treatment plant expansion, interceptor rehabilitation, and south treatment plant aeration system rehabilitation.
CURRENT PROJECTS
| WW0605 | East and West Interceptor Inspection and Evaluation |
| WW0801 | Lift Station Rehabilitation - Horseshoe, Kingfisher and Oyster Point |
| WW0802 | Collection System Rehabilitation Program |
| WW0901 | Treatment Plant Flow Diversion (North to West) |
| WW0902 | Treatment Plants Emergency Power |
| WW0904 | East & West Interceptor Rehabilitation - Phase II |
| WW0905 | Lift Station Rehabilitation |
| WW0906 | South WWTP Aeration System Rehabilitation |
| WW0907 | Lift Station Rehabilitation - Mayfield Park |
| WW1001 | NWWTP Chlorine Bldg. and Gray Water System |
| WW1002 | Lift Station Rehab |
| WW1003 | Emergency Power Pumps at Lift Stations |