City of Sugar Land - 2010-2014 CIP Program Total Summary
| USES |
2010 |
2011 |
2012 |
2013 |
2014 |
TOTAL |
| Airport |
$770,000 |
$832,000 |
$830,000 |
$162,500 |
$2,750,000 |
$5,344,500 |
| Drainage |
4,500,000 |
2,750,000 |
100,000 |
100,000 |
7,450,000 |
$14,900,000 |
| Municipal |
5,981,400 |
7,185,000 |
1,810,000 |
400,000 |
1,000,000 |
$16,376,000 |
| Parks |
7,161,,000 |
16,065,000 |
9,375,000 |
8,655,000 |
8,575,000 |
$49,831,000 |
| Streets |
42,011,022 |
3,580,000 |
1,245,000 |
850,000 |
1,000,000 |
$48,956,022 |
| Traffic |
3,010,000 |
1,044,000 |
1,860,000 |
969,000 |
3,435,000 |
$10,318,000 |
| Wastewater |
3.195,000 |
7,710,000 |
34,400,000 |
2,325,000 |
2,300,000 |
$49,930,000 |
| Water |
10,185,000 |
3,940,000 |
3,260,000 |
4,405,000 |
550,000 |
$22,34,000 |
| Surface Water |
10,060,000 |
69,800,000 |
6,000,000 |
|
|
85,860,000 |
| TOTAL |
$86,8713,422 |
$113,176,000 |
$58,880,000 |
$17,866,500 |
$27,060,000 |
$303,855,922 |