SL Logo

City Council

Agenda Request

Agenda Of:

04-06-10

Agenda Request No:

iv-b

Initiated By:

Greg Nichols

Project Manager

Responsible Department:

Public Works

Presented By:

Joe Chesser

Assistant Parks & Recreation DirectorInitials JAC

Department Head:

Mike Hobbs,mrh initial

Director of Public works

 

 

Additional Department. Head (s):

Jim Browne,JB

Director of Parks & Recreation

Subject / Proceeding:

First Colony Park Improvements

Authorize Construction Contract and Approve Budget Reduction of $300,000

Exhibits:

Bid Tabulation

Clearances

Approval

Legal:

N/A

Executive Director:

N/A

Purchasing:

Todd Reed,

Purchasing ManagerTodd Reed - initials_2

Asst. City Manager:

Karen Daly  KD_initials

Budget:

Jennifer Brown,

Budget & Research Director

City Manager:

Allen BogardSIGNATUR

Budget

Expenditure Required:  $

1,030,854.93

Current Budget:  $

1,400,312.75 Available in PK0803

Additional Funding:  $

-300,000.00 in Revenues & Expenditures

Recommended Action

Authorize a construction contract with Millis Development & Construction, Inc. for the First Colony Park Improvements Project Phase I in an amount not to exceed $1,030,854.93 and approve a budget reduction of $300,000 in revenues and expenditures.

Executive Summary

The First Colony Athletic Complex was originally built by the Municipal Utility District serving this area of First Colony and was acquired by the City through annexation in 1997. There have been minor improvements since the park was constructed but several amenities have deteriorated and some have become substandard due to changes in Little League field guidelines.

 

In 2005, the Sugar Land Parks Recreation and Open Space Master Plan was completed and adopted by the City Council. In 2007, a citywide Parks Assessment was performed to identify deficiencies throughout the parks system and in 2008, a PER was performed to identify the design elements and estimated costs for the renovation of the First Colony Park.  All of these assessments/events have led to this project’s inclusion in the CIP.

 

The PER recommended construction of the new restroom and renovation of the existing ballfields in a multi-year, multi-phase approach in order to avoid closure of the entire park during construction of the improvements. This contract will include Phase I Construction.

 

Some of the key goals that will be achieved with this construction contract include:

   

¨      A new restroom/concession building to be constructed between fields 5 and 7 including utilities.

¨      Upgrade fields 1 and 2 with outfield fence relocation, light upgrades and pole relocation, new foul poles, one new scoreboard and relocation of an existing scoreboard.

¨      Tree and landscape removal and replacement to accommodate fence relocation.

¨      Drainage and sidewalk improvements within Phase I limit.

¨      Spectator seating upgrades for accessibility.

                   

On February 18, 2010, four bids were received for the First Colony Park Improvements Project.  The apparent low bidder was Millis Development & Construction, Inc. with a total bid of $1,030,854.93. Upon approval to proceed, we anticipate construction to begin in April and run through October 2010.

 

The Public Works and Parks & Recreation Departments recommend the City Council authorize the execution of a construction contract with Millis Development & Construction, Inc. for First Colony Park Improvements Phase I in an amount not to exceed $1,030,854.93. 

 

As discussed with the City Council in the March 23, 2010 workshop, this project has realized savings compared to the budget estimate.  It is recommended that the budget for this project be reduced by $300,000 in expenditures, offset by a revenue reduction of $300,000 from Certificates of Obligation bond proceeds.

Exhibits

 

Millis Development & Construction, Inc

$1,030,854.93

American Wall Systems

$1,128,307.65

Jerdon Enterprise, L.P.

$1,181,027.10

Gulf Coast Landscape Services Inc.

$1,842,459.00