|
|
City Council |
|||
|
Agenda Request |
||||
|
Agenda Of: |
December 16, 2008 |
Agenda Request No: |
IV-G |
|
|
Initiated By: |
keisha e. seals, engineer iii |
Responsible Department: |
Engineering |
|
|
Presented By: |
keisha e. seals, engineer iii |
Department Head: |
Chris Steubing, P.E. City Engineer |
|
|
|
|
Additional Department. Head (s): |
n/a |
|
|
Subject / Proceeding: |
award of professional services contract to wilbur smith and
associates for the preliminary engineering services for the dairy ashford
widening project Approve Budget Amendment of $9,500 in revenues and expenditures |
|||
|
Exhibits: |
Proposal, Fee
schedule, Project Schedule and
contract |
|||
|
Clearances |
Approval |
|||
|
Legal: |
eugenia cano asst. city attorney |
Executive Director: |
Joe Esch |
|
|
Purchasing: |
Todd Reed purchasing manager |
Asst. City Manager: |
Karen Daly |
|
|
Budget: |
jennifer brown assistant fiscal services director |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
69,500.00 |
|||
|
Current Budget:
$ |
60,000.00 |
|||
|
Additional Funding:
$ |
9,500.00 Revenues &
Expenditures |
|||
|
Recommended Action |
||||
|
Award a professional services contract to Wilbur Smith and Associates for engineering services in an amount not to exceed $69,500.00 for CIP Project STPE01, Dairy Ashford Widening Project and approve a budget amendment of $9,500 in revenues and expenditures in the capital projects fund. |
||||
|
Executive Summary |
||||
|
In 2003, the City
hired a consultant to study the corridor of Dairy Ashford and Spur 41 at U.S.
Highway 90A. The scope included the
development of a feasibility study to determine improvement options for short
and long-term. At the time, the Texas
Department of Transportation was near completion of the U.S. Highway 59
improvements and in the design phase of the now completed U.S. Highway 90A
widening. Upon completion of
the U.S. 90A improvements, ownership of the Spur 41 facility was to be
transferred from TxDOT to the City.
The purpose of the feasibility study was to confirm acceptable
operations of TxDOT’s proposed improvements to the U.S. 90A/Spur 41
intersection through design year 2020.
The study was to also confirm acceptable operations of the
intersection, factoring in the existing (2003) and projected future growth in
the Union Pacific rail traffic. The overall
goal was to mitigate delay impacts of expected increases in rail traffic
along the U.S. 90A corridor while providing acceptable access to commercial
properties along Spur 41 between U.S. 90A and U.S. 59. The feasibility
study provided two (2) alternatives for improvement of the corridor: Grade
Separation with an overpass and At-Grade improvements. The At-Grade improvement was recommended in
the final report. During the time of
the feasibility study, the U.S. Highway 90A improvements were not yet
designed and constructed; therefore, the impact of the widening was not taken
into consideration during the analysis of the corridor. The Preliminary
Engineering phase will analyze the current traffic volumes and traffic areas
to determine what impact the widening of U.S. 90A improvements had on the level-of-service
from Dairy Ashford to Julie Rivers and Dairy Ashford to U.S. 59; analyze
future level-of-service (LOS); determine at what year improvements are
warranted (if not existing year, based on LOS ) and design a layout of the
recommended improvement that will satisfy the operational needs in the future
“Build-Out” of the corridor (ie: Business Park, Granite Towers, etc). This project was
identified and submitted to Fort Bend County for inclusion into the 2007
Mobility Bond package. The agreement
provides a 50/50 match for construction funding. The PER is the first phase of moving
towards the design and construction phases and will identify the ultimate
improvements for this section due to the maximum growth and build-out of this
area. Staff solicited Requests for Qualifications (RFQ’s) for the Dairy Ashford Widening PER Project as part of RFQ 2008-10. Selection of the consultant utilized the RFQ process presented at the June 24, 2008 Council Workshop. Seven qualified consultants were short-listed and interviewed. Among the seven, Wilbur Smith and Associates was selected by the Engineering staff for the preliminary engineering services. Wilbur Smith and Associates has performed services for the City on several projects such as the Eldridge Road Underpass Study and University Boulevard North Feasibility Study. The schedule for completion of the PER is six (6) months after award. The Engineering
Department recommends that the City Council award the attached professional
services contract to Wilbur Smith and Associates for preliminary engineering
services for the Dairy Ashford Widening Project (CIP STPE01), in an amount not
to exceed $69,500.00. Funds for this
project are provided by the SLDC through an agreement with the City. At the December 2, 2008 SLDC meeting, the Board
approved an additional $9,500 in funding over the original $60,000 budgeted. An
amendment to the capital projects budget is also being requested to reflect
the $9,500 in funding for STPE01 and a corresponding increase in revenues to
reflect reimbursement of $9,500 from the SLDC. |
||||
|
Exhibits |
||||












