Agenda Request |
||||
|
Agenda Of: |
10-16-07 |
Agenda Request No: |
IV C |
|
|
Initiated By: |
Clayton E. Taylor, ROW Manager |
Responsible Department: |
Public Works |
|
|
Presented By: |
Mike Leech Assistant Public Works Director |
Department Head: |
Mike Hobbs, Director of Public Works |
|
|
|
|
Additional Department. Head (s): |
N/A |
|
|
Subject / Proceeding: |
CenterPoint Energy Street Light Agreement Letter for Lighting
University Boulevard Authorize Execution of Agreement Letter |
|||
|
Exhibits: |
Maps Pictures Agreement Letter |
|||
|
Clearances |
Approval |
|||
|
Legal: |
meredith wilganowski, assistant city attorney |
Executive Director: |
N/A |
|
|
Purchasing: |
Jennifer E. Montgomery Purchasing Manager |
Asst. City Manager: |
Karen Glynn |
|
|
Budget: |
Jennifer Brown Assistant Fiscal Services Director |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
179,893.00 |
|||
|
Amount Budgeted/Reallocation: $ |
200,000.00 |
|||
|
Additional Appropriation: $ |
N/A |
|||
|
Recommended Action |
||||
|
The Public Works Department recommends that City Council authorize the City Manger to execute the CenterPoint Energy Street Light Agreement Letter to initiate installation of street lights on University Boulevard at a cost not to exceed $179,893.00. |
||||
|
Executive Summary |
||||
|
In a workshop discussion held in late 2001, City Council gave direction to continue the City’s Urban Beautification efforts on University Boulevard in providing ornamental street lights and traffic signals as part of our infrastructure design. As a result, a decorative traffic signal was installed at the intersection of University Boulevard and Lexington, which is at the entrance of the University of Houston. In addition, the roadway design and construction incorporated the appropriate foundations, electrical conduit, and grounding necessary to support lighting structures identical to those along S.H. 6 and Eldridge. The foundations electrical conduit and grounding were installed in conjunction with the roadway construction as it was determined that there would be cost savings over having Center Point install the foundations electrical conduit and grounding during the construction of the lighting. Since the area is undeveloped, with the exception of University Boulevard, limited power capacity was available to light the roadway. Per contract with the City, Center Point is now in the process of extending electric capacity to the Brazos River Park in a sufficient amount to allow Public Works to request a street lighting plan and an agreement letter to initiate installation of the street lights. It is anticipated that the construction of this electric power infrastructure by Center Point will be complete by the third week of October. The proposed lighting design includes University Boulevard from U.S. 59 south to the Commonwealth Boulevard bridge. The proposal received from Center Point is for $179,893.00. The proposed agreement includes:
The mounts, poles, luminaires and layout of the street light system is consistent with the existing system along both S.H. 6 and Eldridge and University Boulevard north of U.S. 59 installed by Telfair (see attached pictures).
Funding is available through CIP ST0806–University Boulevard Illumination Project. The funded balance is $200,000.00. Upon execution of the agreement letter, material will be ordered and a construction order is placed by Center Point Energy. Installation should be completed in approximately six months, weather permitting. A lighting system for the Commonwealth Bridge over Ditch H is currently under design as well. Center Point is not performing the design nor will they provide the light poles, etc. as per policy that they no longer maintain or provide bridge lighting. It is anticipated that the remaining fund balance within ST0806 will be sufficient to fund the construction of the bridge lighting system. The Public Works Department recommends that City Council authorize the City Manger to execute the Center Point Energy Street Light Agreement Letter for lighting University Boulevard. |
||||
|
Exhibits |
||||




Subject: Street Light
Agreement Letter September
21, 2007
University Boulevard (Hwy. 59
to Commonwealth)
Sugar Land Service Area
CenterPoint Energy (Company)
agrees to furnish, install, own and maintain street lighting service in the above
noted area subject to the Lighting Services Rate schedule and the corresponding
Service Rules and Regulations Relating to the Provision of Delivery Service to
Retail Customers. As shown on the
Illumination layout, the requested installation has been designed in accordance
with the Illuminating Engineering Society of North America (I.E.S.N.A.)
recommendations.
This installation consists
of:
38, 250 watt, high-pressure
sodium, 25,500 lumen, double-arm Houstonian style luminaires mounted to
Sweetwater poles (19 poles) painted black and serviced by underground
conductors. The current monthly Lighting Services Rate schedule fee per street
light is $12.00 per lamp.
34, 250 watt, high-pressure
sodium, 25,500 lumen, Houstonian style luminaires mounted to direct embedded
Traditionaire poles (34 poles) painted black and serviced by underground
conductors. The current monthly Lighting Services Rate schedule fee per street
light is $20.10 per lamp.
The total cost for this
request is $179,893.00. Please remit
this payment attached to this signed and completed agreement letter and return
to: CenterPoint Energy, 4500 S. Shaver, Bldg. D, Houston, TX 77034, Attn:
Stefanye Fojt
If this is in accordance with
your understanding and acceptance, please indicate so in the spaces provided
below and return the below needs to the Service Consultant that provided you
with this agreement letter:
• A signed copy of this
street light agreement letter
• Payment of the above
mentioned construction costs
If you have any questions
regarding the street light installation, please contact me at (713) 945-3245.
Sincerely,
Stefanye
S. Fojt
Associate
Service Consultant
Street
Lighting Division
Please print all entries
below except for signature.
Approved and accepted this
___________ day of ___________, 2007.
Signature
___________________________________________________________
Printed Title
___________________________________________________________
Printed Name
___________________________________________________________
Mailing
Address___________________________________________________________