City Council |
|||||||||||||||||
|
Agenda Request |
||||||||||||||||||
|
Agenda Of: |
October 16, 2007 |
Agenda Request
No: |
IV B |
|||||||||||||||
|
Initiated By: |
Mike Hobbs,
Director of Public Works |
Responsible
Department: |
Public Works |
|||||||||||||||
|
Presented By: |
Mike Hobbs, Director of Public Works |
Department
Head: |
Mike Hobbs,
Director of Public Works |
|||||||||||||||
|
|
|
Additional
Department. Head (s): |
Mike Goodrum,
Community & Environmental Director |
|||||||||||||||
|
Subject /
Proceeding: |
Animal Control
Facility Approval of
Change order No. 1 and Authorization to Purchase |
|||||||||||||||||
|
Exhibits: |
Change Order No.
1 |
|||||||||||||||||
|
Clearances |
Approval |
|||||||||||||||||
|
Legal: |
Joe Morris, City
Attorney |
Executive
Director: |
|
|||||||||||||||
|
Purchasing: |
Jennifer
Montgomery Purchasing
Manager |
Asst. City
Manager: |
Karen H. Glynn |
|||||||||||||||
|
Budget: |
Jennifer Brown Assistant Fiscal
Services Director |
City Manager: |
Allen Bogard |
|||||||||||||||
|
Budget |
||||||||||||||||||
|
Expenditure
Required: $ |
Net $0 |
|||||||||||||||||
|
Amount
Budgeted/Reallocation: $ |
N/A |
|||||||||||||||||
|
Additional
Appropriation: $ |
N/A |
|||||||||||||||||
|
Recommended
Action |
||||||||||||||||||
|
The Public Works Department requests that City Council approve the execution of Change Order No. 1 in the deductive amount of $237,067 with Zekkours Construction Co., Inc. and approve the purchase of a pre-engineered modular building from Houndquarters, Inc. in the amount of $211,248. |
||||||||||||||||||
|
Executive
Summary |
||||||||||||||||||
|
On September 4, 2007, City Council authorized execution of a contract with Zekkours Construction Co., Inc. in the amount of $751,580 for the turnkey construction of a 4,300 s.f. animal control facility. Chapter 2155 of the Texas Government Code stipulates that all public works contracts in excess of $25,000 will include payment and performance bonds in the full amount of the contract value. On or about September 27, 2007, Zekkours Construction Co., Inc. was notified by its insurance agency that the bond underwriter would not provide bonds in the full amount of the contract value of $751,580. Subsequent discussions with the underwriter revealed that the denial for bonding was based solely on the contractor’s limited experience with bonded public works projects. To date, Zekkours Construction has successfully completed in excess of ten projects under contract with the City, of which two required bonding, with the largest being $180,000. The underwriter stated that he would bond a project up to $600,000 in value until such time that the underwriter felt the firm deserved consideration for an increase in its bonding capacity. It should be noted that in an effort of good faith and in order to keep the project on-schedule, Zekkours Construction had ordered the pre-engineered modular building and made a down payment of $23,472. Staff is proposing that in order to keep the project on schedule, City Council approve the following proposals:
In discussions with the Legal and Purchasing Departments, there is agreement that the provisions of Chapters 252 and 271 of the Texas Local Government Code permit both of the above-specified actions. The net impact of this action to the City will be a savings of $25,819 and, more importantly, the ability to complete construction of the facility within the contract completion time of December 31, 2007. The Public Works Department requests that City Council approve the execution of Change Order No. 1 in the deductive amount of $237,067 with Zekkours Construction Co., Inc. and approve the purchase of a pre-engineered modular building from Houndquarters, Inc. in the amount of $211,248. |
||||||||||||||||||
|
Exhibits |
||||||||||||||||||
Animal Control Facility CIP No. MU0701. Change Order No. 1
CIP CHANGE ORDER REQUEST
|
10.3.2007 |
Change Order #: |
1 |
|
|
|
Department: |
CIP PW |
|
|
|
Notice to Proceed Date: |
|
|
|
Project
Title: |
Project
#: |
|
David Gaines |
Phone Ext: |
281 275-2359 |
|
|
Contractor: |
Contract
Date/Time: |
Change Order
Description:
Price Impact:
|
$761,580.00 |
||
|
B. Current Change Order Amount: |
||
|
C. Previous Change Orders: |
$0.00 |
|
|
D. Cumulative Change Order Amount (B +
C): * |
($237,067.00) |
|
|
E. Percent of Original Contract (D ¸ A): |
-31.13% |
|
|
F. Revised Contract Amount (A+D): ** |
$524,513.00 |
|
*Cumulative change order amount (Line D) must not exceed 25%
of original PO amount.
**If new purchase order total (Line F) exceeds $25,000 and original purchase order amount (Line A) is less than $25,000, change order must be taken to City Council for approval.
Schedule Impact:
|
Original
Contract Time (Days): |
100 |
Original
Completion Date: |
12.31.2007 |
|
Current
Change Order (Days): |
|
|
|
|
Previous
Change Orders (Days): |
0 |
|
|
|
Revised
Contract Time (Days): |
100 |
Revised
Completion Date: |
12.31.2007 |
Vendor Acknowledgement: Date: 10/03/07
Program Manager: Date:
Budget Approval: Date:
(Required only if Line B =
$10,000 - $14,999)
(Required only if
Line B = $15,000-$24,999)
Distribution:
1 EXECUTED ORIGINAL to City Secretary
1 EXECUTED ORIGINAL to Requesting Department (for
Contractor)
1 COPY for Purchasing/Accounting Use