Subject / Proceeding: |
PUBLIC HEARING TO CONSIDER A STRATEGIC PARTNERSHIP
AGREEMENT WITH FORT BEND COUNTY MUNICIPAL UTILITY DISTRICTS NO. 67, 68, 69,
111, & 112, (NEW TERRITORY COMMUNITY) Public Hearing |
|||
|
Exhibits: |
Proposed Strategic Partnership Agreement (hard
copy available) |
|||
|
Clearances |
Approval |
|||
|
Legal: |
|
Executive Director: |
Jim Callaway Community Development |
|
|
Purchasing: |
N/A |
Asst. City Manager: |
N/A |
|
|
Budget: |
N/A |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
N/A |
|||
|
Amount Budgeted/Reallocation: $ |
N/A |
|||
|
Additional Appropriation: $ |
N/A |
|||
|
Recommended Action |
||||
|
Conduct public hearing and receive citizen input regarding the proposed strategic partnership agreement. |
||||
|
Executive Summary |
||||
|
This is the first of two public hearings regarding a Strategic
Partnership Agreement between the City of Sugar Land and Fort Bend County
Municipal Utility Districts 67, 68, 69, 111, and 112 ( 1.
Pre-annexation Services, including: a.
Fire Protection Services:
i.
The City and the Districts will jointly fund the construction of a Fire
Station to serve the area.
ii.
The Districts will pay for services under the current fire services
agreement, but will pay the 20% Out of City fee after 1/01/2008. 2.
Debt Reduction Fund: a.
This fund accumulates all proceeds from the Out of City service fee
paid by the Districts on municipal services, as well as an annual
contribution from the City from the proceeds of sales tax collections from
the Riverpark annexation. The funds in
this account will be used to defray the costs of annexing the districts. 3.
Full Purpose Annexation a.
This provision provides that the Districts will be annexed
simultaneously for full purposes no earlier than 01/01/2017 and no later than
the date at which all of the Districts have paid off their outstanding debt. 4.
Wastewater Treatment Plant a.
This provision provides that the City will, at its own cost, expand the
current NT WWTP to serve both the New Territory Community and the City in
general, up to a maximum capacity of 10.5 MGD. It also requires certain odor abatement
provisions, tree buffers, and landscape screening. 5.
GRP Services: a.
This provision provides the terms and conditions under which the City
will include the Districts in its Groundwater Reduction Plan. The proposed SPA document is attached for your review. |
||||
|
Exhibits |
||||