City Council

Agenda Request

Agenda Of:

5-20-08

Agenda Request No:

V-E

Initiated By:

Robert Hazelrig

Program Coordinator

Responsible Department:

Support Services

Presented By:

Sereniah Breland

Support Services Director

Department Head:

Sereniah Breland

Support Services Director

 

 

Additional Department. Head (s):

 

Subject / Proceeding:

Police/Courts Carpet Replacement

Authorize Contract

Exhibits:

Contract

Buy Board Flooring Quotation Form

First Floor Highlighted Carpet Replacement Floor Plan

Second Floor Highlighted Carpet Replacement Floor Plan

Clearances

Approval

Legal:

Meredith Wilganowski,

Assistant City Attorney

Executive Director:

 

Purchasing:

Linda Symank

Director of Fiscal Services

Asst. City Manager:

Karen Daly

Budget:

Jennifer Brown

Assistant Fiscal Services Director

City Manager:

Allen Bogard

Budget

Expenditure Required:  $

68,824.45

Amount Budgeted/Reallocation:  $

68,824.45

Additional Appropriation:  $

n/a

Recommended Action

Authorize execution of contract with Mannington Commercial in the amount of $68,824.45.

Executive Summary

Currently 13,455 square feet of flooring, on the first and second floors of the Police and Courts Building, has become worn, torn, and in need of replacement. This carpet was originally installed in January, 2001.  The Police Department, Facilities Management and the Johnston, LLC Assessment recommends 1,495 square yards of carpet and 36 linear feet of VCT tile be replaced. The proposed project includes material, labor, and insurance for moving furniture and replacement of existing flooring. The remaining flooring, which is not in high traffic areas, would be replaced in the future. 

 

Staff recommends that the City Council authorize a contract with Mannington Commercial to perform these services. In an attempt to maximize pricing and the level of service, the purchase is being made through a cooperative purchasing agreement with Buy Board, Purchasing Agreement 2-06.  Mannington Commercial will begin the project upon execution of a purchase order. 

 

The proposed project duration is 30 days, with substantial completion projected for August 8, 2008.  Funds are available in MU0801, Facilities Improvements, with an unencumbered balance of $121,557.60.

Exhibits