|
|
City Council |
|||
|
Agenda
Request |
||||
|
Agenda Of: |
January 15, 2008 |
Agenda Request
No: |
IV C |
|
|
Initiated By: |
Shashi Kumar,
P.E. |
Responsible
Department: |
Engineering |
|
|
Presented By: |
Shashi Kumar,
P.E. Drainage Engineer |
Department
Head: |
Christopher L.
Steubing, P.E., City Engineer |
|
|
|
|
Additional
Department. Head (s): |
Mike Hobbs Public Works
Director |
|
|
Subject /
Proceeding: |
Award of
Engineering Services Contract with Dannenbaum Engineering in the amount of
$77,247 for the Design of Proposed Diversions From Covington Woods and Sugar
mill to Eldridge Rd. |
|||
|
Exhibits: |
||||
|
Clearances |
Approval |
|||
|
Legal: |
Eugenia Cano, Assistant city
attorney
|
Executive
Director: |
Jim Callaway Community
Development |
|
|
Purchasing: |
Linda Symank Director of
Fiscal Services |
Asst. City
Manager: |
|
|
|
Budget: |
Bryan Guinn Budget Manager |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure
Required: $ |
77,247 |
|||
|
Amount
Budgeted/Reallocation: $ |
150,000 |
|||
|
Additional
Appropriation: $ |
N/A |
|||
|
Recommended
Action |
||||
|
Award Engineering Services Contract for the Final Design of proposed stormwater diversions to Eldridge Rd. to Dannenbaum Engineering Corporation for an amount not to exceed $77,247. |
||||
|
Executive
Summary |
||||
|
During the expansion
of Eldridge Rd., the City staff worked with the Texas Department of
Transportation (TxDOT) to allocate additional capacity in the Eldridge Rd.
storm sewers to accommodate proposed stormwater diversions from the Covington
Woods area. These diversions were
intended to alleviate some of the flooding concerns in the Covington Woods
watershed, as identified in the Covington Woods Drainage Study. The proposed street intersections that were
included in the original design were: Woodchester, Bournewood, and
Greywood. The design plans for these
diversions were prepared in 2005 and were approved by TxDOT. The construction
of the proposed diversions was put on hold pending the completion of the
detailed Sugar Mill Drainage Study.
One of the scopes included in the Sugar Mill Study was to evaluate the
impact of the proposed diversions on Ditch A-22. The Sugar Mill study was recently
completed. This study has confirmed
that there are no adverse impacts on Ditch A-22 from the proposed
diversions. As such, the construction
of the identified improvements can move forward. The Sugar Mill
Drainage Study has also identified a number of improvements in the A-22
watershed to alleviate flooding concerns.
One of the identified improvements includes stormwater diversion from
Rolling Mill Dr., which also ties into Eldridge Rd. As a result, a contract was negotiated with
Dannenbaum to perform the following:
The main scope of this engineering services contract is to update the
original design plans and specifications to reflect current (changed) field
conditions. Also, the scope of
services is expanded with additional services to determine if additional
diversions can be incorporated into the original design. The proposed additional (new) intersections
include: Rolling Mill Dr. and Greenbriar/ Linden Dr. If the proposed additional (2) diversions
can be incorporated into the original design, the plans will be updated to
reflect these changes. The revised
plans will then be resubmitted to TxDOT for permitting purposes. Dannenbaum
Engineering Corporation (DEC) was selected as the consultant to perform this
design work, since they were also the Engineer of Record on the original
plans. A detailed scope of work/
proposal from DEC is attached to this agenda request. The total contract amount for all the
identified scope of services is not to exceed $77,247. The duration of this engineering contract
is 180 calendar days. Construction of the originally proposed improvements is
budgeted and identified in the FY 2009 CIP.
The estimated preliminary construction cost is $900,000. This 2005 cost estimate will be refined as
part of this design contract, and will also include costs for two additional
diversions, if included. The revised
cost estimated would be available prior to the finalization of the FY 2009
CIP. Funding Availability Funding for this project was budgeted in the FY 2008 CIP. There is currently $150,000 available in DR0801 for design related project expenses that are funded from CO’s and WCID #1. |
||||
|
Exhibits |
||||
|
|
||||