City Council |
|||
|
Agenda Request |
||||
|
Agenda Of: |
11-21-06 |
Agenda Request No: |
IV B |
|
|
Initiated By: |
greg nichols, public works project manager |
Responsible Department: |
Public Works |
|
|
Presented By: |
SUELLEN STAGGS,
DIRECTOR OF UTILITIES |
Department Head: |
suellen staggs, director of utilities |
|
|
|
|
Additional Department. Head (s): |
Mike |
|
|
Subject / Proceeding: |
Commonwealth /University utility Line extentions to serve the Sugar
Land Memorial Park accept low bid and AUTHORIZE contract |
|||
|
Exhibits: |
bid tab |
|||
|
Clearances |
Approval |
|||
|
Legal: |
n/a |
Executive Director: |
n/a |
|
|
Purchasing: |
n/a |
Asst. City Manager: |
karen glynn |
|
|
Budget: |
Linda Symank Director of Fiscal Services |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
708,160.00 |
|||
|
Amount Budgeted/Reallocation: $ |
570,000.00 budgeted/545,150.00 unencumbered |
|||
|
Additional Appropriation: $ |
200,000.00 from Utility CIP fund Balance |
|||
|
Recommended Action |
||||
|
Public Works and
Utilities staff is requesting that City Council accept the low bid and
authorize a contract between the City and Kingsley Constructors, Inc., for
the Commonwealth /University Utility Line Extension Project to serve the Sugar
Land Memorial Park in an amount not to exceed $708,160.00 and authorize the
appropriation of $200,000 from the Utility CIP fund balance to project No.
WA0606. |
||||
|
Executive Summary |
||||
|
The scope of this project is to provide water and
sanitary sewer service for the new We will be installing utility lines from the
Avalon subdivision along Commonwealth, crossing ditch H and continuing down Commonwealth/University Utility Line Extension Project, WA0606, has an
unencumbered balance of $545,150.00.
The additional appropriation of $200,000.00 will be taken from the
Utility CIP fund balance and will cover construction cost with a 5%
contingency. The project bids exceeded the budget estimated last year, which
is due to continued escalations in materials and construction costs. These
additional costs will be included in our annual evaluation and calculation of
connection fees. Staff is
requesting that City Council accept the low bid and authorize a contract
between the City and Kingsley constructors, Inc., for the Commonwealth
/University Utility Line Extension Project to serve the Sugar Land Memorial Park
in an amount not to exceed $708,160.00 and authorize the appropriation of
$200,000 from the Utility CIP fund balance to project No. WA0606. |
||||
|
Exhibits |
||||
CITY OF
BID OPENING:
November 2,2006 @ 11:00 AM
BIDDER 5%
BID BOND ADDENDUM TOTAL BID
Kingsley Constructors,
Inc. Ö Ö $708,160.00
Jerdon Enterprise,
L.P. Ö Ö $787,827.00
C.E. Barker, Ltd. Ö Ö $1,153,814.07