|
|
City Council |
|||
|
Agenda Request |
||||
|
Agenda Of: |
11-21-06 |
Agenda Request No: |
III J |
|
|
Initiated By: |
mike wilkinson, project manager |
Responsible Department: |
public works |
|
|
Presented By: |
mike hobbs, director of public works |
Department Head: |
mike hobbs, director of public works |
|
|
|
|
Additional Department. Head (s): |
n/a |
|
|
Subject / Proceeding: |
main street reconstruction project – cip no. st0706 authorize design contract |
|||
|
Exhibits: |
consultant’s proposal project location map |
|||
|
Clearances |
Approval |
|||
|
Legal: |
n/a |
Executive Director: |
n/a |
|
|
Purchasing: |
n/a |
Asst. City Manager: |
karen glynn |
|
|
Budget: |
LINDA SYMANK, DIRECTOR OF FISCAL SERVICES |
City Manager: |
allen bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
95,054.00 |
|||
|
Amount Budgeted/Reallocation: $ |
1,310,000 |
|||
|
Additional Appropriation: $ |
N/A |
|||
|
Recommended Action |
||||
|
Executive Summary |
||||
|
The Public Works
Department has solicited a proposal from Cobb Fendley & Associates, Inc.,
to provide engineering services for the Main Street Reconstruction
Project. The Main Street
Reconstruction Project is located from the north side of the Main Street
Bridge to the existing new pavement just north of Seventh Street. Additional services include geotechnical and
surveying necessary for project design. The contract scope of work is as
follows: PER Phase ·
Review record
as-built drawings of adjacent intersecting streets, First Street through
Seventh Street ·
Review
hydraulics and hydrological data and flood plain ·
Provide
drainage and storm sewer analysis ·
Traffic
study, including possible traffic calming elements at Main Street and Seventh
Street (in accordance with the University Boulevard extension study) Design Phase ·
Prepare design plans, technical specifications and special
conditions to contract documents ·
Review traffic flows and counts and prepare a construction/traffic
phasing plan ·
Prepare itemized bid form and proposal (City will supply
format) Funding for the Main Street Reconstruction Project design phase has been budgeted in the FY2007 Capital Improvement Program with construction scheduled for late FY2007. This portion of Main Street is one of the City’s few remaining asphalt streets and was last overlaid in 1990. The scope of the Main Street Reconstruction Project will consist of removing and replacing the existing asphalt pavement with 7” concrete pavement from the Main Street Bridge to Seventh Street in order to bring the street into compliance with current City pavement and drainage standards. The installation of new concrete pavement will include an expanded storm sewer system with additional inlets, up graded outfalls, utility adjustments, sidewalk replacement with access ramps, and driveway grade adjustments. Prior to starting construction, staff will coordinate with the area homeowners, police department, fire department, parks staff, Saint Theresa’s Church, and provide contact numbers to each. Following is a proposed
schedule for the project: ·
Preliminary
engineering – December 2006 – February 2007 ·
Final design
– March 2007 – May 2007 (60 calendar
days) ·
Bid phase –
May 2007 – June 2007 (Depending upon US 90A and SH 6 Overpass Construction Progress) ·
Construction
– June 2007 –November 2007 (150 calendar days) Cobb Fendley & Assocaites, Inc has agreed to perform the proposed engineering service within 180
days from notice to proceed for an amount not to exceed $95,054. Funding for the requested engineering
services is available in CIP No. ST0706 with a current balance of $1,310,000.
These funds are part of the last issuance of the 1999 voter approved GO
Bonds. |
||||
|
Exhibits |
||||


