|
|
City Council |
|||
|
Agenda Request |
||||
|
Agenda Of: |
11-07-06 |
Agenda Request No: |
IV B |
|
|
Initiated By: |
David gaines CIP Project Manager |
Responsible Department: |
Public Works/Airport |
|
|
Presented By: |
Mike Public Works Director |
Department Head: |
Mike Public Works Director |
|
|
|
|
Additional Department. Head (s): |
Phillip Savko Aviation Director |
|
|
Subject / Proceeding: |
Authorize Design Contract with KSA Engineers, Incorporated |
|||
|
Exhibits: |
Engineering Services Contract |
|||
|
Clearances |
Approval |
|||
|
Legal: |
na |
Executive Director: |
Joseph Esch Business & Intergov. Rel. |
|
|
Purchasing: |
n/a |
Asst. City Manager: |
n/a |
|
|
Budget: |
Jennifer Brown Assistant Fiscal Services Director |
City Manager: |
Allen Bogard |
|
|
Budget |
||||
|
Expenditure Required: $ |
98,800 |
|||
|
Amount Budgeted/Reallocation: $ |
100,000 |
|||
|
Additional Appropriation: $ |
0 |
|||
|
Recommended Action |
||||
|
Staff recommends City councils authorization to award a
contract with KSA Engineers, Inc. for the design of the |
||||
|
Executive Summary |
||||
|
KSA Engineers, Inc. is being recommended as the firm to design the new T-Hangar Complex located south of the new Sugar Land Regional Airport Terminal. The design scope will be 96 t-hangars (in 6 separate buildings see break down below), a 1900 SF pilots area, and a 1900 SF public waiting, staff work area and equipment storage area. The design will be such that it may be bid and built in phases due to budgetary constraints. The base bid will include 81 t-hangar units, which will accommodate all 79 current t-hangar customers, at an estimated cost of $3 million. Add alternates will be for the pilots area, the waiting area/work area, and the remaining 15 t-hangars. The overall design will encompass the following:
The following are some of the amenities proposed to be included in the project:
Under the terms of the Citys contract with KSA Engineers, Inc., the firm will provide the following services:
The original budget for construction was set at $2 million, and increased to the current budget of $3 million. Due to recent construction cost increases, the project will be phased to assure that the end product is within the $3 million budget, and still meet the current need for t-hangars. The bids that we receive for construction of the project will dictate what amenities and other improvements beyond the 81 T-hangars we are able to construct. Funding for the design phase services will be from CIP No. AP0601 with an available balance of $100,000. Design is to be completed by April 2007 with an anticipated start date of construction in August 2007, with completion in May 2008. |
||||
|
Exhibits |
||||
