City Council

Agenda Request

Agenda Of:

10-17-06

agenda request no:

V C

Initiated By:

pete polito, project manager

responsible department:

public works/utilities

Presented By:

mike hobbs

director of public works

department head:

mike hobbs,

director of public works

 

 

additional department. head (s):

suellen staggs, utility director

Subject / Proceeding:

telfair surface water pump station project – sw0601

accept low bid and authorize construction contract

Exhibits:

bid tab

project location map

consultant’s recommendation letter

Clearances

approval

Legal:

n/a

executive director:

n/a

Purchasing:

n/a

asst. city manager:

karen glynn

Budget:

jennifer brown

assistant fiscal services director

city manager:

allen bogard

Budget

Expenditure Required:  $

397,605.80

Amount Budgeted/Reallocation:  $

SW0601 - $104,854.26   SW0701 - $600,000.00

Additional Appropriation:  $

 

Recommended Action

Public Works staff is requesting that City Council accept the low bid and authorize a contract between the City and Deep South Construction, Inc., for construction of the Telfair Surface Water Pump Station Project in an amount not to exceed  $397,605.80.

Executive Summary

On Thursday September 28, 2006, three bids were opened for the Telfair Surface Water Pump Station. The apparent low bidder was Deep South Construction, Inc., with a total bid of $397,605.80 and a 190-calendar day completion time. CP&Y, the City’s consultant for the project, completed a reference review and evaluation and provided a letter of recommendation indicating Deep South Construction, Inc., is capable of completing a project of this size and nature. Staff is also familiar with Deep South Construction through their recent successful completion of a distribution system extension capital project and similar infrastructure work completed in the City and ETJ for development projects. 

 

The scope of the Telfair Surface Water Pump Project is construction of a raw surface water pump station and supply line located near the intersection of SH 6 and Brooks Street (see location map).  The surface water pump station will be a submersible type station located on the south bank of the Brooks Lake Diversion Channel near the AMIL Gates.  The project’s transfer line consists of approximately 1,100 L.F. of 12-inch pipe from the pump station location to the northeast edge of the Telfair development, which includes crossing SH 6 and Ditch “H”.

 

Completion of the project will allow the transfer of raw surface water to the Telfair development for use in landscape irrigation and filling of static level detention lakes.  The proposed use of surface water by Telfair will provide the City with subsidence district credits.  The credits will enable the City to reduce the costs of our proposed surface water plan by allowing us to downsize or delay construction of the future surface water plant or bank the credits for use in future years. The credits stand to represent an avoidance of costs with a payback of less than 18 months.  Using the raw surface water will cost the city about $300,000 per year less than it would cost to produce the same amount of treated surface water.  The savings or cost avoidance will be realized every year.

 

Funding for this project’s construction was budgeted in the FY2007 Capital Improvement Program.  There is currently $104,854 in CIP No. SW0601, with an additional $600,000 in supplemental funding available in CIP No. SW0701.  Contractor Construction Notice to Proceed issuance is anticipated for early November 2006 with completion scheduled for mid-May 2007.

 

Exhibits

 

 

 

CITY OF SUGAR LAND

 

BID OPENING:  TELFAIR SURFACE WATER PUMP STATION PROJECT

 

DATE:  JULY 6, 2006           PLACE:  CITY HALL           TIME:  10:00 A.M.

           

BIDDER

5% BID BOND

TOTAL BID

Deep South Construction

P

$397,605.80

Jimerson Underground

P

$464,472.00

Peltier Brothers Construction          

P

$468,973.00